Table 1: Rotary-engine air compressor
development and manufacturing project timeline.
Week
|
||||||||||
Task
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
Literature
study
|
x
|
x
|
x
|
|||||||
CAD modeling
|
x
|
x
|
x
|
x
|
x | |||||
Simulation of
models and preliminary optimization
|
x
|
x | ||||||||
Producing and
assembling of the prototype
|
x
|
x
|
x
|
|||||||
Prototype
testing and producing the final deliverable
|
x
|
x
|
x
|
|||||||
Final report
preparation
|
x
|
x
|
x
|
Weekly
progress goals-completed/failed/ongoing:
-Group meets weekly to discuss progress and any
upcoming/ongoing/recently finished tasks and any problems/improvements
possible.
Week
1:
Form group & brainstorm project ideas-completed
Research background of project-completed
Week
2:
Finalize project idea-completed-Wankel Engine Air Compressor
Further research into workings, components, manufacturing
techniques involved-completed
Finish Project Proposal-completed
Begin CAD modeling-Prototype 1 completed
Week
3:
CAD modeling continues-Prototype 2 completed, design
revisions needed to complete housing and design details
Discuss and finalize manufacturing techniques for each
piece-completed
Week 4:
Parts list finalized-completed
Parts list finalized-completed
Begin ordering parts-completed
Create Project Proposal Presentation PowerPoint-completed
Final CAD model delivered-completed
Create Project Proposal Presentation PowerPoint-completed
Final CAD model delivered-completed
Week
5:
Finalize prototype design if not already finished-completed
Computer-Aided Simulations and Analysis begins-completed
Computer-Aided Simulations and Analysis begins-completed
Begin manufacturing prototype-completed-main housing printed, manufacturing plans finalized for other parts
Week
6:
Continue manufacturing prototype (3D printing, machining, etc.)-completed-prototype crankshaft machined, rubber gasket cut to shape, prototype lid laser cut
Computer-Aided Simulations and Analysis continues-completed
Finish Simulations and Analysis on prototype along with final revisions to design-static simulations completed
Begin work on final report-completed
Computer-Aided Simulations and Analysis continues-completed
Finish Simulations and Analysis on prototype along with final revisions to design-static simulations completed
Begin work on final report-completed
Week
7:
Finish manufacturing and assembly of prototype-completed
Begin physical analysis on any parts already manufactured-completed
If necessary, manufacture revised parts for final assembly-completed
Continue work on final report, draft due-completed
Prototype deliverable due-completed
Continue work on final report, draft due-completed
Prototype deliverable due-completed
Week
8:
Finish analysis and testing of physical prototype-completed
Continue manufacturing of final components of final assembly-completed
Continue work on final report-completed-rough draft submitted
Begin work on final presentation-completed-rough draft submitted
Continue work on final report-completed-rough draft submitted
Begin work on final presentation-completed-rough draft submitted
Week
9:
Finish manufacturing of final deliverable-completed
Finished final report-completed
Final report due-completed-submitted
Continue work on final presentation-ONGOING
Poster created and submitted for freshman design competition-ONGOING
Final report due-completed-submitted
Continue work on final presentation-ONGOING
Poster created and submitted for freshman design competition-ONGOING
Week
10:
Final presentation due-
Final deliverable due-
Final deliverable due-